Saturday 28 September 2013

Day Thirty

The past four weeks have certainly flown by.  I reckon by the end of October the whole thing will be completed.

I thought I'd do a quick recap of everything that has been completed so far;

Loft emptied
Scaffolding erected
Hole knocked in gable end to form new window
Steel installed above bedroom door to support new steels required to hold the new loft floor
Holes cut in internal brickwork to take new steels
Steels lifted in via crane
Steels installed and holding brickwork completed
New loft floor joists installed
Old loft hatch closed off
Old Office emptied ready for conversion work
Floor installed
Hole cut through ceiling into loft
Woodwork for new walls in
First layer of insulation in
First fix wiring and plumbing in
More insulation in
Yet more insulation in
Stairs in and fitted

Roll on next week....