Tuesday 10 September 2013

Day Twelve

It was a fairly quiet day today.  The electrician was here first thing to take a look at the job.
All looked straight-forward enough until he checked the main fuse box and advised us that he would need to upgrade it.

We then had a visit from Building Control who came to check the structural work already completed.  The steel work and floor joists were all fine so we are clear to proceed with laying the floor etc.

Unfortunately the floor will be delayed until Thursday as the plumber will be here and he needs to bring some pipework up into the loft.  Once he has done that we can then get the floor down.

So, all being well everything will start moving again on Thursday, which means it'll be peace and quiet at home on Wednesday....nice.