Friday 18 October 2013

Day Fifty

A quiet day compared to yesterdays happenings.

The new airing cupboard has now been built (slightly wider than first planned to avoid all those pipes) and there is very little else left to do before we can get all the cosmetic work started.


We also had the quote through from the decorator as well as confirmation that the bathroom flooring has arrived.

The weekend is going to be all out painting which will set us up for the remaining tasks next week.

Saturday
Do the undercoat in the new loft space - Office, Bathroom, Landing & Stairs
Buy some stain for the woodwork
Buy some gloss for the new doors - Office & Bathroom
Collect Bathroom flooring from the store

Sunday
Apply the stain to the skirting in the Office & Bathroom
Paint the first & second coats (at least getting around where all the fittings are going)

Monday
Electrician will be here to fit all the lights, switches, sockets etc (hopefully including some new lighting for the old office space)
Continue with painting (in evenings as there will now be light)

Tuesday
Fit the bathroom flooring
Move some furniture up into the loft before the stairs are completed

Wednesday
Plastering all the remaining spots in the old office and landing (including removing the old loft hatch and boarding up the underside of the new stairs
Fitting the new bathroom door (should be delivered today)

Thursday
Fit the spindles, handrails etc to the stairs to finish them off

Friday
We might just be finished ?????


Not long after this we'll have the painter in to do the rest of the existing hall, stairs and landing.
Then finally the carpet will be fitted.

Then we really will be finished.