Tuesday 15 October 2013

Day Forty Seven

The skirting boards were fitted today along with the finishing touches to the door frames and also the cupboard doors for the loft storage space.


We also had a visit from a Painter/Decorator to price up painting the hall, stairs & landing.  Now that it's such a huge space it's not the sort of task I would like to complete on my own.  I'm happy to do the new office and bathroom in the loft though.

Hopefully by the end of the week the bathroom door and office door (fire door) will be fitted.  The build work on the loft rooms will then be completed.

The electrician is ready to put all the fittings in but we are pushing him back until next Monday so that we can do the painting beforehand.

All being well the builders will start on the old office space next week.  The door ways for the old office (4th bedroom) and old airing cupboard will be removed so that the space is opened up onto the existing landing.

I can't wait for this part to happen but it may cause a bit of a mess.  Everything has happened behind these doors so far so it's been easy to hide all of the work (and dust).